VERIFIED UPDATE · OCTOBER 9, 2026
October 20 · 6 p.m. · Brighton City Council
One-year data-center moratorium: first reading approved October 6; second reading scheduled October 20. Adoption and effective date remain pending.
Meeting details, official agenda and next steps → · DCAP proposed municipal checklist →
FORT LUPTON · SEPARATE INVESTIGATION · UPDATED OCTOBER 12, 2026
The land, water and money trail.
Records establish an annexation and ownership investigation near Fort Lupton and Lochbuie. Final data-center approval, an operator, power demand and industrial water availability have not been established by this review. A connection to Project Silo has not been established.
VERIFIED RECORDS UPDATE · OCTOBER 12, 2026 · EVENING
Follow the deeds. Follow the studies. Follow the money.
SENT: At 8:48 p.m. Mountain time on October 12, DCAP emailed Weld County’s Recording Department at crstaff@weld.gov requesting eight recorded instruments for the Fort Lupton and Project Silo parcels, complete exhibits and available transfer/financial attachments. Sending was verified in Proton’s Sent folder. No acknowledgment or request number has been verified yet.
No fees authorized. An itemized estimate and express written approval are required before any chargeable work. Ordinary electronic copies were requested; no paid subscription or certified copies were authorized.
Fort Lupton: the assessor’s transfer chain
For parcel 147122200006, account R8967608, the live Weld assessor history shows Rancho de Los Tiempos Buenos Partnership LLC → William T. Matlock Trust → Fort Lupton 117 LLC. Instruments 5043377 and 5047448 were recorded July 25 and August 14, 2025. The latter entry reports a $2,937,800 sale dated August 11. These are verified assessor entries; the deed scans and their full terms remain requested, not obtained.
Project Silo: a separate parcel and ownership trail
The July 2025 pre-application identifies parcel 147134000073, at 15518 County Road 4. Weld’s land account R8052899 lists Willard John Family Trust. Requested records include instruments 2472572, 3111890, 3111891, survey 4898437 and special-review instrument 3979537. These records do not establish a shared developer or owner with Fort Lupton.
What comes next
- Fort Lupton: Complete annexation and development files; applicant, developer and vendor identities; completed and draft studies; utility commitments; contracts, invoices, incentives and cost allocation.
- Lochbuie: The Consor invoice and work product for “8/24 – 1.21 LLC annex,” plus correspondence, payment and applicant reimbursement records.
- Water: Complete files for permits 334092 and 53620. The original affidavit says 53620; a slide’s 53630 is incorrect.
- Project Silo: Review responses to existing Brighton, Weld and Adams County requests before sending overlapping supplements. Obtain the written withdrawal, its scope and City acceptance.
Submission status: The new Weld recorded-document request is sent. The five separate southern Weld drafts SW-01–SW-05 remain drafts; this email does not submit them. The Fort Lupton study/vendor request was sent at 10:07 p.m.; official intake acceptance remains pending. The Lochbuie send is unverified; Hudson and Weld Cielo drafts and the water supplement remain unsent.
Fort Lupton evidence + requested instruments October 20: show up
Eight recorded instruments requested October 12
- Fort Lupton parcel 147122200006 / R8967608: 5043377, 5047448 and 4612745 (recorded exemption RECX20-0026).
- Project Silo parcel 147134000073 / R8052899: 2472572, 3111890, 3111891, 4898437 and 3979537.
Earlier official trail
Lochbuie’s October 1, 2024 packet lists a $97.50 Consor engineering payment labeled “8/24 – 1.21 LLC annex,” paid September 26. Fort Lupton’s December 12–13, 2024 affidavits identify wells 334092 and 53620 for the proposed annexation. Weld’s April 21, 2025 agenda references an April 7 letter about “1.21 Annexation Nos. 1–7.” None of these alone establishes final data-center approval.
Primary sources
- Fort Lupton official parcel account
- Project Silo official land account
- Original Fort Lupton water affidavits
- Lochbuie October 1, 2024 packet
- Weld April 21, 2025 agenda
- July 2025 Silo pre-application
Video source: Possible Data Center Coming to Ft. Lupton. The source deck and screenshots were reviewed; the complete audio was not verified.
VERIFIED TRANSMISSION STATUS · OCTOBER 12, 2026
Questions published. Request status stays separate.
- Brighton: Silo written withdrawal, study authors, jobs and public costs supplement sent to the City Clerk at 10:02 p.m. Mountain time; verified in Sent. R000429-092326 cross-referenced. No new acknowledgement verified.
- Fort Lupton: 1.21 annexation, studies, vendors, jobs and costs email sent to the City Clerk at 10:07 p.m.; verified in Sent. Official-form/intake acceptance remains pending.
- Weld Recorder: Eight deed/recorded instruments requested at 8:48 p.m.; verified in Sent. Full instruments and acknowledgement not yet obtained.
- Lochbuie: Identified Consor invoice and supplemental scope prepared; send attempt unverified. Do not count as submitted.
- Hudson/Cielo and Weld Cielo/Global AI: Drafts prepared. Hudson official form completed. These new requests remain unsent.
No fees are authorized. Itemized written estimate and express written DCAP approval are required before chargeable work. The email workspace’s credential-protection error blocked the remaining sends; recovery was attempted. Publishing these questions does not submit the drafts.
Read all 96 critical questions. A study inventory records what must be obtained; it does not establish that a study exists, was reviewed or cleared a project.